From WABA, who attended this week's meeting.
The construction bid [for the Metropolitan Branch Trail] will go out soon for Phase I, and construction is estimated to begin June 2016, with an estimated completion date of August 2016. Phase II will begin November 2017, the section west of Selim Road, which includes the bridge over Georgia Ave., will begin in November 2018 and phase completion is estimated for November 2019.
The record remains open until May 24 at 7 p.m. If you’d like to submit your comments to the record, email Gaila Lescinskiene at[email protected].
Phase I is two blocks of sidepath that dead end. It's in Phase II that the key pieces are built.