In May, Fairfax County started working on the Mount Vernon Highway Trail Project. The project will build a 10-foot wide sidepath along parts of Mount Vernon Highway between Grist Mill and Washington Mill Park.
This $6.5 million, two-mile stretch is part of the Potomac Heritage National Scenic Trail between Richmond Highway (Route 1) and Southwood Drive and in accordance to the Countywide Trails Plan.
It will also build a 14' trail bridge over Dogue Creek. There are some existing, and shoddy, trail segments and these will not be rebuilt as part of this project.
Relocations of utilities began in June 2021 and are expected to be completed by September 2021. Utility relocations including gas, electric, and communication lines are necessary to accommodate the proposed trail. The Washington Gas line relocation is in process. The construction of the trail project is expected to start Fall 2021.
The project is to be completed in Winter 2022.